(a) Under Detroit
(1) American Cruiser Company, Trenton, Michigan
First contract awarded 1 April 1941. Ten (10) 110′ wood submarine chasers were built
on three contracts (nine delivered at the Navy Yard, New York and one (SC-684)
delivered at the Naval Station, New Orleans. Last vessel was delivered 23 August
1943. The contract cost for the ten vessels totaled $1,337,000.00.
(2) Robinson Marine Construction Company, Benton Harbor, Mich.
First contract No. S-83462 awarded 1 April 1941 for two 110′ wood submarine chasers.
A total of 12 – 110′ wood submarine chasers were built on this contract, its extension
to two more on 30 July 1941, and on contract No. S-546. The contract cost of the 12
vessels totaled $1,668,000.00.
Note: Two vessels had been completed and a third keel laid when this yard was transferred
from SupShip, Detroit to the jurisdiction of the Supervisor of Shipbuilding, USN, Chicago
on 6 June 1942. The last vessel was completed on 25 September 1943.
(3) Dachel-Carter Shipbuilding Company, Benton Harbor, Mich.
First contract awarded 6 June 1941. Twenty wood hull vessels of five different types
were built on five contracts, including:
| Number |
Type |
| 2 |
BYMS |
| 2 |
SC (110′) |
| 8 |
YMS |
| 4 |
PCS |
| 4 |
ATR |
* There was evidence in certain files that the Robinson Marine Construction Company had
previously built two Bombing Target Boats, C-1828 and C-1829 on contract No. S-6917. The
records are not complete but they were apparently completed late in 1940, and some
assistance was given in the inspection by Lt.(jg) COWN of the SupShip Bay City office,
although the general cognizance was apparently under the INM Chicago.
Of these vessels none were completed prior to the transfer of the jurisdiction to the
Supervisor of Shipbuilding, USN, Chicago on 6 June 1942, although four vessels had been
launched and were nearing completion. The last vessel was completed 22 August 1944. The
total contract cost of the 20 vessels totaled $6,376,800.00.
(4) Chris-Craft Corporation, Algonac, Cadillac and Holland, Michigan (and later Grand Rapids, Michigan 1-1-45)
This developed to be the second largest producing yard in value of the subject supervisory
offices. First contract was awarded 17 December 1941. The supervision, although under the
cognizance of the SupShips, first at Detroit and later at Bay City, was directly under
the supervision of the Asst. SupShip at Algonac. See also his separate history —
Exhibit 2. This corporation produced on 18 contracts and five extensions:
| Number |
Length |
Type |
| 105 |
36′ |
Picket boats (harbor) |
| 1,238 |
36′ |
LCP(L) Landing Craft Personnel (Large) |
| 2,535 |
36′ |
LCP(R) Landing Craft Personnel (Ramp) |
| 600 |
36′ |
LCV Landing Craft Vehicle |
| 7,806 |
36′ |
LCVP Landing Craft Vehicle & Personnel |
A grand total of 12,284 craft at a contract value of over $70,000,000.00 in addition to
over $5,000,000.00 worth of additional material on 379 maintenance and spare parts
contracts and 754 orders of less than $5,000.00.
The last craft under these contracts were delivered on 9 January 1946, being delayed by
a work stoppage August 29 to November 21, 1945.
(5) Gar Wood Industries, Marysville, Michigan
Note: This contractor was also directly under the Asst. SupShip, Algonac.
First contract awarded 24 December 1941. 145 boats were built on three contracts and one
extension, divided by type as follows:
| Number |
Type |
| 75 |
36′ Navy Picket Boats (Harbor) |
| 70 |
24′ Plane Personnel Boats, Mark I |
At a total contract value of $1,135,792.50. The last boat was delivered on 6 November
1943.
(6) Victory Shipbuilding Company, Macatawa, Holland, Michigan
First contract awarded 30 April 1942. Six wood-hull vessels were built on two contracts:
| Contract No. |
Number |
Type |
| NObs-179 |
2 |
110′ Wood Submarine Chasers |
| NObs-838 |
4 |
YTL |
At a total contract price of $500,000.00. The supervision of this contractor was
transferred from SupShip Detroit to the jurisdiction of the Supervisor of Shipbuilding,
USN, Chicago, on 12 December 1942, at which time the first subchaser had been launched
but not completed. The last vessel was completed 21 September 1943.
(b) Under Bay City
(1) Foster Boat Company, Charlevoix, Michigan
First contract 6 April 1942. 247 small boats of five different types, including:
| Number |
Type |
| 150 |
33′ Plane Rearming Boats |
| 30 |
24′ Plane Personnel Boat Mk. 2 |
| 50 |
24′ Plane Personnel Boat Mk. 4 |
| 27 |
17′ Line Handling Boats |
| 40 |
9′ Sailing Dinghies |
These were built on seven contracts and two modifications, with some interruptions
between contracts. The last boat was delivered 4 January 1946. The total value of all
contracts, less cancellations, amounted to $769,447.70, not including a termination
claim of about $35,000.00.
(2) Eddy Shipbuilding Company, Bay City, Michigan
First contract 13 July 1942. 130 small boats of three different types, including:
| Number |
Type |
| 30 |
33′ Plane Rearming Boats |
| 60 |
28′ Whale Boats |
| 20 |
24′ Plane Personnel Boats Mk. 2 |
| 20 |
24′ Plane Personnel Boats Mk. 4 |
These were built on four contracts and one modification, with a long interruption of
over a year between two of the contracts. Concurrent with the last contract, this
yard had a small repair contract to recondition two 24′ Plane Personnel Boats, which
had been loaned by the Navy for research purposes in connection with the test of a
newly proposed system of propulsion.
The last boat was delivered on 25 September 1945. The total value of all contracts
amounted to $362,663.00.
(c) Under Assistant Supervisor of Shipbuilding, Algonac
(1) Hacker Boat Company, Mount Clemens, Michigan
First contract 6 July 1945. 25 — 36′ Bombing Target Boats. First boat delivered 11
December 1945. Estimated last boat to be delivered in June 1946. Total value of
contract was $186,425.00.
Defoe Shipbuilding Company Subcontractors
The Defoe Shipbuilding Company did considerable subcontracting during their program,
using at least thirty-five (35) subcontractors in Michigan. Of these, the following have
been shown on Exhibit 1, as being the most prominent and generally prefabricating major
parts of steel hulls for various vessels; also those where inspection supervision was
maintained by SupShip, Bay City.
| Name |
Dates |
Principal Parts Manufactured |
Approx. Value of Work |
| Valley Welding & Boiler Co., Bay City, Mich. |
6-13-41 / 10-6-44 |
PC Rudders, LCI(L) Sterns & Rudders |
$1,140,000.00 |
| Baker Perkins, Inc., Saginaw, Michigan |
9-5-41 / 12-29-44 |
PC Small Tanks, DE Bows, LCI(L) Pilot Houses |
$1,189,000.00 |
| Hugh Lee Iron Works, Saginaw, Michigan |
9-12-41 / 9-25-44 |
PC Deck Houses, DE Deck Houses, LCI(L) Bows |
$720,000.00 |
| Whitehead & Kales Co., River Rouge, Michigan |
1-7-43 / 10-16-44 |
DE Bulkheads, DE Bottom Sections, DE Deck Sections, LCI(L) Main Hull Sections |
$4,835,000.00 |
| Wickes Boiler Co., Saginaw, Michigan |
4-5-43 / 12-7-44 |
DE Boiler Assemblies, DE Deck Houses |
$180,000.00 |
| Nicholson Terminal & Dock Co., Ecorse, Michigan |
4-28-43 / 8-22-44 |
PC, completed 18 vessels including installation of machinery, etc. |
$2,260,000.00 |
| Allied Steel & Conveyor Co., Detroit, Michigan |
3-4-44 / 9-25-44 |
LCI(L) 47 Deck Houses fabricated (in four sections) |
$470,000.00 |
All of the above contractors and subcontractors and the period of time covered by their
work are shown graphically on Exhibit 1. Broken vertical lines indicate periods of no
Navy work between contracts.
In addition to the above subcontractors where duty stations were maintained more or less,
the Defoe Shipbuilding Company also employed at least twenty-nine other subcontractors in
Michigan, where the inspection was carried on by periodic visits of the SupShip
representatives, or by representatives of the Inspector of Naval Material, Detroit
District.
A graphical presentation of the series of Navy shipbuilding contracts awarded the Defoe
Shipbuilding Co. is shown on Exhibit No. 3. This supplements the information previously
described in paragraph 3(b).